TMX — Taxi Media Experience

Management Progress Report · Through 11 Aug 2026
11 August 2026

Executive Summary

Epic Status

EpicStatusProgressNote

Timeline — Gantt by Epic (Apr–Oct 2026)

Complete In progress Planned Blocked / pending decision Today (11 Aug)
Swipe horizontally to see the full timeline.
Engineering deadline: end of September 2026 (internal QA & sign-off). Go-live & production release are pending the taxi-provider partnership decision.
QA & Testing (internal): field testing on real taxis is not possible yet. 5 internal tablets are being procured (estimated arrival from China in early September); testing will run on office operational vehicles.
Go-live to real taxis — pending decision: the taxi-provider partnership (Vector) is not yet confirmed. Go-live and production release are scheduled after the partnership decision.