TMX — Taxi Media Experience

Management Progress Report · Through 2 Sep 2026
2 September 2026
Latest update: Development-tablet hardening advanced: Player QC is now 36/41 checks (88%), while Tools remains at 10%, bringing active EPIC-08 QC to 49%. EPIC-07 remains 38%; API test-gating, QA sign-off, tablet readiness, and real-taxi go-live are still open dependencies.

Executive Summary

Overall Progress
Development scope · EPIC-00–07
92%
EPIC-00–06 are complete; EPIC-07 is at 38%. External tablet and taxi-provider gates are excluded.

Epic Status

EpicStatusProgressManagement note
EPIC-00 · Setup & HiringComplete100%Team, budget, hiring, and project setup complete.
EPIC-01 · Planning & ArchitectureComplete100%Architecture direction, role alignment, and milestones established.
EPIC-02 · Core Platform SetupComplete100%Repositories, deployment baselines, Backend, CMS, and Android foundations ready.
EPIC-03 · Playlist EngineComplete100%Campaign/playlist workflow, synchronization, playback, and reporting available.
EPIC-04 · Device ControlComplete100%Device controls, targeting rules, and sensor integration available.
EPIC-05 · Interactive Ads & QRComplete100%Side-banner interaction, popup experiences, and brand-provided QR creative available.
EPIC-06 · Entertainment ModuleComplete100%Multimedia playback and entertainment launcher available.
EPIC-07 · QA & Targeting (Internal)In progress38%Three repo test/CI baselines are green; Backend gate, QA matrix, and targeting validation remain open.
EPIC-08 · Hardening (Internal)In progress49%Active development-tablet QC: Player 88%, Tools 10%; production-tablet checks remain hardware-gated.
EPIC-09 · Pilot (Internal)Planned0%Office-vehicle validation follows tablet readiness.
EPIC-10 · Go Live PrepBlocked / pending0%Waiting for taxi-provider partnership decision.
EPIC-11 · Production ReleaseBlocked / pending0%Partner-gated after go-live preparation.

Timeline — Gantt by Epic

EPIC-00–02 · Foundation
EPIC-03–06 · Product delivery
EPIC-07 · QA & Targeting
EPIC-08–09 · Internal validation
EPIC-10–11 · Go-live/release
Engineering target remains end of September 2026 for internal QA and sign-off. Real-taxi go-live and production release remain partner-gated.
Next management checkpoint: Player evidence/sign-off, Tools checklist evidence, Backend test gate, completed QA matrix, and confirmed production-tablet readiness.
Go-live to real taxis: pending the taxi-provider partnership decision. Internal development and office-vehicle validation continue independently.