Latest update: Overall system development stands at 97% and core product features remain 100% complete. Work this period was limited to small backend refinements (richer device information and an adjustable connectivity threshold). Internal tablet stability holds at 86%. A correction on testing: internal acceptance testing is in fact essentially complete at 99% (85 of 86 scenarios passed, last executed 11 Sep), not the 34% reported previously — that figure was a snapshot taken on 8 Sep and never refreshed against the team’s test records. What remains before engineering sign-off is formal evidence and approval, not test execution. The sample tablets for road testing have not arrived and the supplier has given no delivery date, so internal road testing is now formally on hold; live taxi rollout continues to wait on the taxi partner agreement.
Executive Summary
Overall Progress
Development scope · EPIC-00–07
97%
Core functional platform is ready (97%). Hardware validation and operational fleet deployment are excluded, pending tablet delivery and partner readiness.
- Core product (100%): Ad playlist, video playback, remote device control, interactive ads, and entertainment features are fully built.
- Testing & QA readiness (99%): Every application runs automated checks before each release build, and internal acceptance testing has now passed 85 of 86 scenarios, with testing carried out through 11 Sep. One scenario remains, covering how the system de-prioritises a campaign that has already reached its view target.
- Internal device stability (86%): Internal test tablets hold at 86%; the remaining items are defect evidence and formal sign-off rather than new development. No change this period.
- Attention point: With testing substantially complete, the remaining work before the end-September engineering target is formal sign-off — collecting defect evidence and approval on the internal tablet checks — plus the hardware checks that cannot start until the sample tablets arrive.
- External dependencies: The five sample tablets have not arrived and the supplier has given no delivery date, four days past the 10 Sep target. Road testing in office vehicles cannot start until they do, so that work is now on hold rather than merely scheduled. Rollout in actual taxis begins once the taxi partner agreement is confirmed.
Timeline — Gantt by Epic (Apr–Oct 2026)
Complete
In progress
Planned
Blocked / external dependency
Today (14 Sep)
Swipe horizontally to see the full timeline.
Next management checkpoint: Formal engineering sign-off on the completed internal testing, a firm delivery date from the tablet supplier, and the taxi partner decision.
Go-live to real taxis: pending the taxi-provider partnership decision. Internal development and office-vehicle validation continue independently.