Latest update: Internal tablet testing is finished on the team’s side — every check on both tablet applications has passed and the supporting evidence is attached; internal device stability rises from 86% to 95%, and only the final formal sign-off remains. Overall development holds at 97%. New this period: advertisers can download a campaign performance report as a PDF, filtered by media and date, and the campaign list now loads page by page so it stays fast as the number of campaigns grows. The PDF download still needs one more backend release before it works in the live environment. The tablet applications received further stability fixes. The sample tablets have still not arrived and the supplier has given no delivery date; live taxi rollout continues to wait on the taxi partner agreement.
Executive Summary
Overall Progress
Development scope · EPIC-00–07
97%
Core functional platform is ready (97%). Hardware validation and operational fleet deployment are excluded, pending tablet delivery and partner readiness.
- Core product (100%): Ad playlist, video playback, remote device control, interactive ads, and entertainment features are fully built. The flexible campaign content form was completed on 15 Sep: the advertising team can now configure campaigns for any screen layout, with the system enforcing which slots are mandatory and which media types each slot accepts.
- Testing & QA readiness (100%): Every application runs automated checks before each release build, and internal acceptance testing is complete — all 86 scenarios passed.
- Production deployment (done): The backend system was released to its production environment on 15 Sep, with the deployment automatically checked and verified before going live and a documented fall-back to the previous version if it is ever needed. This removes the last technical step between finished software and running service.
- Internal device stability (95%): The tablet team has completed every check on both applications and attached the supporting evidence (up from 86%). The remaining step is the formal review and sign-off by engineering leadership, not further testing.
- New reporting feature: Advertisers can now download a campaign performance report as a PDF, filtered by media and date range. It is built and working in the test environment; it becomes available in the live environment with the next backend release, which should go out before the content management system is published live.
- Attention point: With building and testing complete, the only remaining work before the end-September engineering target is formal sign-off — the evidence is already in hand, so this is administrative and well within the week that remains. The genuine risk is external: the hardware checks cannot start at all until the sample tablets arrive, and there is still no delivery commitment from the supplier.
- External dependencies: The five sample tablets have not arrived and the supplier has given no delivery date, now almost two weeks past the 10 Sep target. Road testing in office vehicles cannot start until they do, so that work is now on hold rather than merely scheduled. Rollout in actual taxis begins once the taxi partner agreement is confirmed.
Timeline — Gantt by Epic (Apr–Oct 2026)
Complete
In progress
Planned
Blocked / external dependency
Today (23 Sep)
Swipe horizontally to see the full timeline.
Next management checkpoint: Formal engineering sign-off on the completed internal testing, a firm delivery date from the tablet supplier, and the taxi partner decision. Of these, only the first is within the team’s control.
Go-live to real taxis: pending the taxi-provider partnership decision. Internal development and office-vehicle validation continue independently.